Phase 1: Pre-Deployment
Complete these items before any on-site work begins.
Project Planning
- Define project scope and target reactor(s)
- Identify key stakeholders (operations, engineering, IT, safety)
- Establish success criteria and KPIs
- Complete Management of Change (MOC) process
- Schedule deployment windows with operations
Technical Assessment
- Document current control system architecture
- Identify PLC model and firmware version
- Map all relevant I/O points and tags
- Review existing PID tuning parameters
- Collect 3-6 months of historical process data
- Document safety system interfaces
Infrastructure Requirements
- Verify network connectivity to control system
- Allocate IP addresses for Acaysia devices
- Confirm firewall rules and network segmentation
- Provision rack space and power for edge device
- Establish secure remote access (if required)
Documentation
- Obtain P&IDs for target process
- Collect equipment datasheets (reactors, heat exchangers)
- Review operating procedures
- Document alarm setpoints and safety limits
Phase 2: Installation
Physical installation of Acaysia hardware.
Hardware Installation
- Mount Acaysia edge device in control room/MCC
- Connect power (verify UPS backup if required)
- Connect Ethernet to control network
- Verify LED status indicators
- Label all connections per plant standards
Network Configuration
- Configure static IP address
- Verify connectivity to PLC (ping test)
- Verify connectivity to Acaysia cloud (if applicable)
- Test DNS resolution
- Configure NTP time synchronization
Initial Software Setup
- Complete initial device registration
- Apply latest firmware updates
- Configure system credentials
- Set up user accounts with appropriate roles
- Configure backup schedule
Phase 3: Configuration
Configure Acaysia for your specific process.
Communication Setup
- Configure OPC UA or EtherNet/IP connection
- Map all required PLC tags
- Verify read access to process variables
- Verify write access to control outputs (in safe mode)
- Test communication failover behavior
Process Model Configuration
- Input reactor specifications (volume, heat transfer area)
- Configure reaction parameters (if known)
- Set operating ranges for all variables
- Import historical data for model training
- Validate initial model predictions
Safety Configuration
- Configure output limits (min/max/rate)
- Set up watchdog timer parameters
- Configure fallback PID setpoints
- Define alarm thresholds
- Test manual override functionality
- Verify SIS status integration (read-only)
Integration
- Configure HMI/SCADA integration
- Set up alarm routing
- Configure historian data export
- Set up email/SMS notifications
Phase 4: Shadow Mode
Acaysia observes and learns without affecting control.
Shadow Mode Activation
- Confirm all configuration is complete
- Enable Shadow Mode in Acaysia dashboard
- Verify data collection is active
- Notify operations team of shadow mode start
Model Training (Minimum 2-4 weeks)
- Collect data across normal operating range
- Include grade changes and transitions
- Include startup and shutdown sequences
- Document any process upsets or anomalies
- Monitor model accuracy metrics daily
Shadow Mode Validation
- Compare Acaysia predictions vs. actual outcomes
- Review recommended control actions
- Validate constraint handling
- Achieve model accuracy targets (>95% prediction accuracy)
- Document findings and tuning adjustments
Shadow Mode Exit Criteria
- Model accuracy meets acceptance criteria
- No unexplained anomalies in recommendations
- Operations team comfortable with system behavior
- Safety review completed and approved
Phase 5: Advisory Mode
Acaysia provides recommendations; operators execute.
Advisory Mode Activation
- Brief all shifts on advisory mode operation
- Enable Advisory Mode in dashboard
- Configure recommendation display on HMI
- Establish feedback mechanism for operators
Advisory Mode Operation (Minimum 2-4 weeks)
- Track recommendation acceptance rate
- Document operator feedback on each shift
- Refine recommendations based on feedback
- Measure theoretical performance improvement
- Address any operator concerns or questions
Advisory Mode Exit Criteria
- Recommendation acceptance rate >80%
- Operators confident in recommendation quality
- Demonstrated performance benefit
- No safety concerns raised
- Operations and engineering approval for closed-loop
Phase 6: Closed-Loop Control
Acaysia takes direct control of specified outputs.
Pre-Activation
- Final safety review meeting
- Confirm operator training complete
- Verify all failsafe mechanisms tested
- Schedule activation during low-risk period
- Ensure engineering support available
Closed-Loop Activation
- Notify operations of mode change
- Enable closed-loop control in dashboard
- Monitor closely for first 24-48 hours
- Document any manual interventions
- Collect operator feedback
Performance Monitoring
- Track KPIs vs. baseline
- Monitor safety metrics
- Review any fallback events
- Document process improvements
- Calculate ROI metrics
Phase 7: Post-Deployment
Ongoing support and optimization.
Documentation
- Update P&IDs with Acaysia integration
- Document final configuration
- Create operating procedures for Acaysia
- Update emergency procedures
- Archive all deployment documentation
Training
- Complete training for all operators
- Train maintenance staff on hardware
- Document escalation procedures
- Establish refresh training schedule
Ongoing Operations
- Establish regular performance review meetings
- Set up automated reporting
- Schedule quarterly safety reviews
- Plan for software updates
- Identify expansion opportunities